Trilogy West Tower Concrete Foundations

Construction works at Cybarco’s ambitious project, Trilogy Limassol Seafront, are in full swing and progressing according to schedule. The concrete foundations of the West Tower were poured on Friday 20 September 2019. Over 130 people worked on the construction of the West Tower foundation; an endeavour which took approximately 24 hours, with over 2,500m³ of concrete specifically designed for the towers. In total, 4 placing pumps were used for 300 loads of concrete. For the foundation, over 700 tonnes of reinforcement were also laid out across 8 layers, while over 350 test cubes were taken, and more than 100 slump tests completed. Additional checks took place during trial phases and throughout the duration of recent works. East Tower and North Tower coming soon...